Rs 1,850 cr likely to be spent on Char Dham prog: Gadkari
National

Rs 1,850 cr likely to be spent on Char Dham prog: Gadkari

Agency News

New Delhi, Nov 28: An amount of Rs 1,850 crore is likely to be spent on the Char Dham Programme in the current financial year, the Government informed on Thursday.

The Char Dham Programme was initially targeted for completion by March, 2020. However, the schedule date of completion of the programme has been delayed mainly due to litigation in the NGT and further Civil Appeal by the petitioner in the Supreme Court, said Union Minister for Road Transport and Highways Nitin Gadkari in a written reply in the Lok Sabha.

Further, the section from Dharasu bend to Gangotri (94km) lies under Bhagirathi Eco- Sensitive Zone on which works can be taken up only after approval of Masterplan by MoEF&CC. The apex court vide order dated August 8, 2019 has disposed of the Civil Appeal and constituted a High Power Committee (HPC) to look into the environmental and other issues related to the Char Dham Programme as per the terms of reference set by the Supreme Court.

The HPC has been mandated to submit its report within 4 months from the date of the order. The date of completion of the programme depends on the report of the HPC and approval of Masterplan for Bhagirathi Eco-Sensitive Zone by MoEF&CC. The projects under Char Dham Programme include widening of existing roads along with adequate, sufficient slope protection by way of erection of retaining walls and breast walls and by deploying drapery system, netting, anchoring, reinforced wall as per Detailed Project Reports.

They also include mitigation measures, stabilisation of chronic landslide and sinking spots, zones as standalone project or part of road widening projects to avoid land slide and safety of road users. Bio engineering methods like hydro seeding are being used for vegetative growth on fragile slopes for their stability. All these measures shall safeguard the highway and habitation against natural calamity.

The works under Char Dham Pariyojna are being implemented on Engineering Procurement and Construction (EPC) mode of contract. These projects are being implemented by 3 executing agencies of Ministry of Road Transport and Highways, viz, Uttarakhand State PWD, Border Road Organization (BRO) and National Highway & Infrastructure Development Corporation Limited (NHIDCL).

For each project, a Supervision Consultant called Authority’s Engineer comprising of a team of Key Experts has been appointed for day-to-day supervision and monitoring of the construction works, which includes monitoring of quality control of the works as required under the contract agreement.

This Supervision Consultant reports directly to the concerned executing agencies in respect of day to day progress and various other aspects of the project. Regular monitoring of progress of the work is done at the level of concerned executing agencies and also at Ministry’s level.

Further, under this EPC mode of contract, the contractor is directly responsible for ensuring quality of the work as well as rectification of defects and maintenance of the project stretch for a period of four years after completion of construction. (UNI)